Tell you the installation process of concrete batch plant.
Installation of concrete batch plant conveyor
1, the conveyor from the bend to start on the back of the frame before and after the frame, then the front and rear legs , conveyor connection is good, bracing and the rack on the hanging lug connected, And then lift the front of the conveyor, connecting the front and rear legs and bracing, and finally the front and rear legs of the anchor bolts.
2, concrete batch plant host and powder batching system installation
Lift the mainframe rack, on the basis of its feet bolts fastening.
3, The installation of the finished product storage hopper
To finished product storage hopper hoist, the leg up, will walk, ladders and finished product storage hopper connection is good.
4, the installation of pellet ingredients system
Lifting the pellet material on the basis of the system, the board will be connected to the two sides of the plate and the board is connected with the card, and then the original aggregate conveyor to start, before and after the rack connection, So that the electric drum at the center of the mixer head hole, and finally the anchor bolts.
5, the installation of cement warehouse
The cement warehouse components in the ground one by one assembly, lifting the cement warehouse, and the lower side of the body bracket less side of the direction towards the powder ingredients system, fixed up and down the warehouse, and finally fixed anchor bolts.
6, the installation of the screw conveyor
Lifting the screw conveyor, the screw conveyor ball hinge and cement warehouse outlet connection, so that the discharge port on the powder hopper feed mouth, and then use the rope to the conveyor and cement warehouse hanging ear connection, and finally to the ground Feet bolts fixed.
7, lift the pump in the right place, connect the output water pipe.
8, the concrete batch plant air compressor on the side of the finished product hopper, with the air pipe to the air compressor outlet and gas control box imports connected to the gas control box exports to the cement warehouse broken arch of the trachea connected.