When faced with the concrete batch plant belt deviation, should be from the conveyor design, manufacture, installation commissioning, use and maintenance and other aspects to solve the problem of tape deviation, such as tape on both sides of the tightness is not the same, the tape two Side of the level is not the same, the roller bracket and other devices are not installed with the direction of the tape running the vertical section and so will cause the belt deviation.
In the concrete batching plants, the belt deviation is a very headache problem, will cause leakage material phenomenon, wear equipment, reduce productivity, and finally affect the efficiency of the entire batching plant.
How to adjust the belt of concrete batch plant?
First of all,The staff need to regularly check the belt, if the edge of the belt wear or belt joints are not parallel, will lead to inconsistent tension on both sides, the staff need to replace the belt. You can also install the self-aligning roller directly on the conveyor.
1, when the belt running, if with the help of the weight and the absence of weight to one side running deviation, that is not the same as the belt tightness on both sides.
2, if the belt running deviation to the left for a moment, a moment to the right running deviation, no fixed direction, tape relaxation.
3, then the drum is not in place to install, or one end of the drum in the back, one end in the front, will lead to the belt at the deviation of the roller, the staff as long as the level of correction roller and parallelism can be.
4, in the concrete mixer no load, the belt is always to the side of the deviation, you can first check the side of the roller support, the side of the roller support side of the belt along the tape running forward 1-2cm, or the other The side roller bracket (or rack) is properly raised;
5, sometimes the roller and the roller part of the sticky material, resulting in the diameter of the increase, resulting in belt deviation, the staff must promptly clean up the adhesive material.