Concrete batch plant production capacity generally according to the concrete project construction schedule and quantity to determine the size.
Concrete batch plant construction schedule should be arranged in accordance with the design of the construction organization.As the site of concrete construction is often intermittent, therefore, should be reasonable arrangements for construction procedures, staggered perfusion time, and pay attention to meet the majority of the construction period required for the amount of concrete in order to reasonably determine concrete batch plant production capacity.
For example, a construction site to be filled with concrete progress: January -1000 cubic, February -1200 cubic, March -1500 cubic, April -2000 cubic, May -2500 cubic, June -1000 cubic. In determining the production capacity of the concrete batch plant should be produced per month 1500m3 more appropriate, short time capacity is insufficient, can be used to add temporary mixing machine solution. If the use is 2500m3, although to meet the construction needs, but the input of the mixer and its ancillary equipment (such as electrical equipment, transportation equipment, etc.) must be increased, it must be increasing the cost of mechanical construction.
Of course, in the actual production process, the concrete batch plant production capacity may be affected by a number of factors, which requires users to do a good job in advance to prevent the normal operation of concrete batch plant production.
Thanks, great article.
Thanks for your valuable comment,Our company are one of leading construction machinery manufacturer in China.