The proper use of concrete batch plant is very important.
1, concrete batch plant should be installed on a solid bench.
2, the console of the concrete mixer, the batching plant operator should be able to see the work of the ministries. The mixer of the electric mixer should be padded with rubber sheet or dry wood.
3, when put the hopper into the correct position, between the hopper and the ground, should add a layer of cushion wood.
4, before the concrete batching plant operation, you should start the mixer no-load operation. Make sure that the direction of rotation of the agitator or blades is the same as the direction indicated by the arrow on the cylinder. For the mixer that reverses the discharge, the stirrer should be positive and reverse run for several minutes and there should be no impact jitter and abnormal noise.
5, before the operation, should be hopper to enhance the test, should observe and confirm the clutch, brake flexible and reliable.
6, when feeding, it is should be strictly prohibited head or hand into the hopper and between the rack. Operation, is strictly prohibited by hand or tool into the mixing tube within the picking material, the material.
7, the concrete mixer operation, when the hopper rises, is strictly prohibited any person to stay in the hopper or through; when the need to repair or clean the pit under the hopper, the hopper should be raised after the chain or insert the pin to lock.
8, to the mixing tank should be carried out in the operation, add a new material should be the original mixing cylinder before the concrete can be discharged before all.
9, during operation, should observe the mechanical operation, when there is abnormal or bearing temperature rise is too high, it should stop inspection; when the need to repair, the mixer should be clear the concrete inside, and then overhaul.